Temporary closure on Exe Estuary Trail

Profile image for PGStrange

By PGStrange | Wednesday, January 30, 2013, 17:28

THERE'S A TEMPORARY closure on the Exe Estuary Trail, between Lympstone station and the Commando Training Camp. The closure - from today until this Friday (1 February) - is by Network Rail and is part of ongoing repairs in the area...

Work has been taking place during the past fortnight to repair a large hole in the trail at Nutwell Court - between Lympstone Station and the Commando Training Camp - which appeared in the cycle way as a result of the severe wet weather just before Christmas. The work has included Devon County Council's contractors underpinning the washed-out sections of the trail.

In addition, Network Rail has also been working in the area. They are repairing the railway bridge, wall and embankment. They require the trail's temporary closure to allow them to complete their heavy work, immediately adjacent to the trail.

The Council is asking cyclists and pedestrians to take care and to pay attention to any warning notices that indicate temporary closure.

Tweet this article
      

Comments

       
  • Profile image for PGStrange

    Re: temporary closure on Exe Estuary Trail. According to Devon County Council, surfacing on the large hole in the Trail at Nutwell Court is programmed for Monday 11 February. The scaffold bridge has already been taken down and there is a temporary surface over the backfilled area where the bridge was.

    By PGStrange at 16:22 on 08/02/13

      Report
              
     
max 4000 characters
        
   

Latest Stories in Exmouth

       
      

Local Vouchers

       
   

Local Jobs

       
   

Search for...

       
        
Min price is bigger than Max price
        
Min price is bigger than Max price
        
Min rent is bigger than Max rent